School Structural Inspection and Action Record
- Version
- v2
- Updated
- 7 October 2026
- Audience
- Maintained and academy schools in England, including responsible bodies, school leaders, estates teams, premises staff and appointed professional advisers.
- Jurisdiction
- england
Blank fields · read-only preview
Use this record for periodic structural inspections or when responding to a suspected or observed structural defect. Record inspections, issues identified, required actions, professional advice, interim controls and the status of remedial actions. Where the building’s condition may require specialist assessment, obtain appropriate professional advice.
School and inspection details
School name
RequiredEnter the name of the maintained or academy school.
School name
Responsible body
RequiredEnter the local authority, academy trust or other responsible body responsible for the school estate.
Responsible body
Building, block or area inspected
RequiredIdentify the building, block, room, elevation or external area covered by this record.
Building or area
Reason for inspection
RequiredSelect all reasons that apply.
Choose all that apply
- Periodic inspection
- Reported visible change in structural condition
- Suspected structural defect
- Environmental event or change in conditions
- Follow-up to a previous issue or action
- Other reason
- Other
If other, please specify
Inspection date
RequiredEnter the date on which the inspection took place.
- Day
- Month
- Year
Inspector name
RequiredEnter the name of the person who carried out or led the inspection.
Inspector name
Inspector role or organisation
RequiredState the inspector’s role and organisation, and identify whether the inspection was carried out by school staff or a professional adviser.
Role or organisation
Inspection planning and scope
Planned interval until the next inspection (months)
Record the planned interval where a recurring inspection programme applies. Set the frequency according to use, construction type and environmental conditions.
Number
Minimum: 0 · Maximum: 120
Construction type or structural system
RequiredSelect all known or relevant construction types.
Choose all that apply
- Traditional brick construction
- Steel frame
- Concrete frame
- Timber frame
- Unknown or not confirmed
- Other construction type
- Other
If other, please specify
Relevant environmental conditions
Select all conditions relevant to the inspection or building.
Choose all that apply
- Flooding
- Nearby watercourse
- Historical mining activity
- Ground conditions
- None known or identified
- Other environmental condition
- Other
If other, please specify
Scope and inspection observations
RequiredDescribe the areas inspected, limitations of the inspection and relevant visible observations.
Scope, limitations and observations
Condition changes and issues identified
Was a visible change in structural condition identified?
RequiredSelect the response that matches the inspection findings.
Choose one
- Yes
- No
- Uncertain; professional advice required
Issues identified
RequiredDescribe each structural issue, including its location, observed condition, apparent extent and any change since a previous inspection. If no issue was identified, state that explicitly.
Issues identified
Is professional structural advice required?
RequiredRecord whether the findings require advice from a professional surveyor or other suitably qualified adviser.
Choose one
- Yes
- No
- Advice already obtained
- To be confirmed
Professional advice and recommendations
RequiredIf advice was obtained or is required, record the adviser or organisation, date, recommendations and any limitations. If not applicable, enter “Not applicable”.
Professional advice and recommendations
Actions, controls and completion
Required actions
RequiredRecord each action required to address or manage the issues identified, including any further inspection, repair, monitoring or escalation.
Required actions
Interim controls
RequiredRecord temporary measures in place while actions are outstanding, such as restricting access, isolating an area, increasing monitoring or arranging urgent advice. If none are needed, state that explicitly.
Interim controls
Action owner
RequiredEnter the person, team or organisation responsible for coordinating the required actions.
Action owner
Action deadline
RequiredEnter the agreed deadline for completing or otherwise managing the required actions.
- Day
- Month
- Year
Action status
RequiredSelect the current status of the required actions.
Choose one
- Not started
- In progress
- Completed
- Managed pending further action
- Closed with no further action required
- Other
If other, please specify
Date actions were completed or managed
Enter the date when the actions were completed or when interim or alternative management arrangements were put in place. If actions remain outstanding, leave this blank.
- Day
- Month
- Year
Evidence and verification of completion or management
RequiredDescribe the evidence reviewed, such as professional advice, inspection notes, work records, invoices, certificates or a follow-up inspection. If actions are outstanding, describe the next review point.
Evidence and verification
Record reviewed by
RequiredEnter the name and role of the person who reviewed this record and its actions.
Reviewer name and role
Review date
RequiredEnter the date on which this record and its actions were reviewed.
- Day
- Month
- Year
Record confirmation
RequiredConfirm that the information recorded is accurate to the best of the reviewer’s knowledge and that outstanding actions have been identified.
- Tick when complete