When to use this procedure
Use this procedure if additional asbestos materials or suspected asbestos materials are uncovered during authorised work at the school.
Procedure
1. Stop work
Stop the work immediately when additional asbestos or suspected asbestos materials are uncovered.
2. Make the area safe
Make the affected area safe before any further work takes place.
3. Reassess the work
Reassess the work in light of the asbestos or suspected asbestos materials that have been uncovered.
4. Continue only after reassessment
Do not continue the work until the work has been reassessed.