This procedure applies where lifting equipment is used at the school or where the school undertakes or controls lifting operations. The arrangements must reflect the equipment, operation, workplace and people involved.
Responsibilities
The school must assign responsibility for coordinating lifting operations to [lifting operations responsible role]. That role must ensure that the equipment and operation are identified, the lifting operation is properly planned, and the relevant controls are communicated to operators and contractors.
Planning must be undertaken by a competent person, identified for the operation as [competent person role]. Lifting operations must be appropriately supervised by [supervising role] and carried out safely.
Identify the equipment and operation
Before an operation is arranged, identify the lifting equipment, lifting accessories, load, workplace and people involved. Record the relevant equipment in the equipment register at [equipment register location].
Where the school provides lifting equipment for use at work or controls its use, the equipment must be safe. This includes equipment operated by school employees or by contractors whose use of the equipment is controlled by the school.
Plan the lifting operation
The competent person must assess the operation and prepare a lift plan or task risk assessment appropriate to the equipment, load, workplace and people involved. The plan must address foreseeable risks, including equipment failure, lifting loads that exceed the equipment's load limit, untrained workers planning or using the equipment, people being struck by moving equipment, and falling loads.
The plan must specify how the load will be attached to the lifting equipment. The load must be securely attached and, where necessary, securely bound to prevent it slipping or falling off.
The plan must identify how people will be protected from moving equipment and falling loads, including any arrangements needed to prevent people from entering the hazardous area or being struck during the operation.
Keep the current lift plan or task risk assessment at [lift plan location] and communicate the relevant controls to operators, supervisors and contractors before the operation begins.
Check strength, stability, positioning and installation
Before use, address the strength and stability of the lifting equipment and the suitability of its positioning and installation for the planned operation. Do not proceed where the equipment, its position or its installation is not suitable for the operation.
Consider whether the workplace or environment could cause damage or deterioration of the equipment, including wet, abrasive or corrosive conditions, and include appropriate controls in the plan.
Check markings and examination status
Before operation, check that the lifting equipment is certified, is marked with its safe working load, and is not overdue for examination. Where equipment marking is relevant, confirm that the required markings are present and legible before use.
Retain the available thorough-examination reports, declarations of conformity and test certificates with the equipment records. Equipment that is overdue for examination or has a relevant defect must not be used until its status has been addressed.
Operate and supervise the lift
The supervisor must confirm that the planned controls are understood and that the operation is carried out in accordance with the lift plan or task risk assessment.
Use only equipment within its safe limits. Attach and secure the load correctly, prevent damage or deterioration of lifting equipment and accessories, and keep people from being struck by moving equipment or falling loads.
Stop the operation if the equipment, load, workplace, positioning, installation, markings, examination status or control arrangements are not as planned. Report the issue through [reporting route] before the operation is allowed to continue.
Contractors and communication
Where a contractor carries out or controls a lifting operation for the school, identify the equipment and operation, confirm the responsible roles, establish the planning and supervision arrangements, and communicate the relevant controls to the contractor and affected school staff.
The school must retain the lift plan or task risk assessment, relevant competence and training information, supervision arrangements, and equipment records for the operation.