School Asbestos Building Work Control Procedure
- Version
- v2
- Updated
- 7 October 2026
Scope and application
This procedure applies to school-controlled or commissioned construction, refurbishment, demolition, repairs and other work that may disturb the building fabric or asbestos materials. It applies to maintained and academy primary and secondary schools in England.
Before work is commissioned or begins, determine whether the proposed work may disturb asbestos materials, including unidentified, presumed or hidden materials. This determination applies to small repairs and to major contracted projects.
1. Assess the proposed work
The person commissioning or controlling the work must determine the asbestos risk arising from the proposed activity. The assessment must consider whether the work may disturb the building fabric or any known, presumed, unidentified or hidden asbestos materials.
Where the work will disturb the building fabric, arrange a relevant refurbishment or demolition survey before the work proceeds. The survey is an intrusive type of survey involving destructive inspection by a trained specialist to identify asbestos materials.
2. Provide asbestos information
Provide the findings of the relevant survey and details of all known or presumed asbestos materials in the work area to the designers and to the people who will undertake the work.
Those undertaking the work must confirm that the information provided is sufficient for the planned activity before work starts.
3. Specify controls and contractor arrangements
Specify suitable risk control measures for the work and ensure that competent contractors are used. A permit-to-work system may be used to implement the required controls.
Confirm whether the proposed asbestos work is licensable, notifiable non-licensable or non-licensable by reference to the applicable HSE advice. Where the work is licensed asbestos work, it must be undertaken by a licensed asbestos removal contractor.
Some small, short-duration tasks may be carried out by non-licensed workers only where they have received appropriate training and the correct risk control measures are used.
4. Coordinate associated building work
Where asbestos removal, encapsulation or other asbestos work is planned, consider the work as part of the wider condition project and assess associated building-system and fabric works that may be needed.
The assessment may include replacement lighting and potentially associated electrical, fire-alarm, IT and CCTV work where these systems are affected by the asbestos work.
5. Proceed only when the arrangements are suitable
Do not allow the planned activity to proceed until the asbestos risk has been determined, the relevant survey has been arranged where required, the available asbestos information has been passed to the designers and workers, suitable controls have been specified, and contractor competence and licensing arrangements have been considered.
Sources
- Managing asbestos in your school or college - GOV.UKDepartment for Education