Confirm applicability
Use this checklist where asbestos-containing or presumed asbestos-containing materials remain in school buildings. Ensure the inspection arrangement reflects the materials, locations, condition and management controls.
Record inspection date
Response required
Enter the date on which this inspection was carried out.
YYYY-MM-DD
Record inspector
Response required
Enter the name of the person carrying out the inspection and, where relevant, their role or organisation.
Name and role or organisation
Locate the asbestos management plan
Use the current asbestos management plan and associated asbestos information to identify the materials and locations to be inspected.
- Yes
- No
- Not applicable
Notes
Record the management plan reference
Response required
Enter the reference, location or link used to connect this inspection record to the asbestos management plan.
Document reference, file path or link
Identify the material and location
Response required
For each material inspected, record whether it is asbestos-containing or presumed asbestos-containing, together with the building, room or area and a sufficiently specific location description.
Material status; building; room or area; precise location
Record the material reference
Enter the reference used in the asbestos register, survey, management plan or other relevant record, where available.
Register, survey or plan reference
Carry out the condition inspection
Inspect the identified material and check its current condition without altering or disturbing it.
- Yes
- No
- Not applicable
Notes
Record the observed condition
Select the description that best records the observed condition at the time of inspection.
Choose one
- No change observed
- Damage or deterioration observed
- Unable to inspect
- Other condition requiring explanation
Describe damage or deterioration
Response required
If damage, deterioration, an unexpected change or an access limitation was identified, describe what was observed and where it was observed. If none was identified, record that no damage or deterioration was observed.
Observed condition and location-specific details
Record photographs where used
If photographs were taken, record the photograph identifiers or storage location and link them to the material and location record.
Photograph identifiers or storage location
Record an assessment where used
If a separate assessment was completed, record its reference and summarise the relevant finding or recommendation.
Assessment reference and relevant finding
Escalate damage or deterioration
Where damage or deterioration is observed, follow the escalation arrangements in the asbestos management plan and notify the responsible person or organisation identified in those arrangements.
- Yes
- No
- Not applicable
Notes
Record the escalation
Response required
Where escalation was required, record who was notified, when they were notified and the reference or method used. If escalation was not required, record that outcome.
Person or organisation, date, method or reference, and outcome
Record remedial action
Response required
Where remedial action is identified, record the action, responsible person or organisation, planned timing and current status. If no remedial action is identified, record that outcome.
Action, responsible person or organisation, timing and status
Update or cross-reference the management records
Record this inspection and any resulting escalation or remedial action in the relevant asbestos management records, or record the cross-reference showing where the information has been entered.
- Yes
- No
- Not applicable
Notes
Record follow-up arrangements
Response required
Enter any follow-up inspection, review or action needed and identify the person or organisation responsible. Where no follow-up is needed, record that outcome.
Follow-up action, responsible person or organisation, and reference or date where applicable
Check the inspection record
Confirm that the material, location, observed condition, supporting evidence where used, escalation outcome and remedial-action information are recorded and linked to the asbestos management plan.
- Yes
- No
- Not applicable
Notes